clough goes into administration
Image: Canva.
  • The disclosure comes as Deloitte finalises administration negotiations with Webuild.
  • Webuild has already agreed to take full control of the Snowy 2.0 and Inland Rail projects for $17.6M.
  • $66.6M is owed to hundreds of unsecured trade suppliers and subcontractors.

Clough Projects went into receivership on December 5th, 2022, when the engineering business’ South African parent, Murray & Roberts, announced it had called in administrators from Deloitte after Webuild SpA pulled a $30 million buyout loan that would have kept the 104-year-old firm afloat.

The initial proposal, agreed in mid-December, provided for Webuild to buy Clough’s Australian workforce and two of its six major projects — the Snowy Hydro 2.0 project in NSW and the Inland Rail project, also on the east coast.

Webuild’s global chief boss Pietro Salini told The Australian Financial Review in December that the company wanted to acquire Clough’s contracts and hire its workers so it could strengthen the Italian group’s operations in Australia.

Approval for the deal for full control of the two federal government funded projects, was to be finalised with the Deloitte administrators by 21 December, but approval was extended by another month to 25 January.

Webuild has already had a good look at Clough, having agreed the previous $350 million buyout and $30 million loan in November before pulling out weeks later and forcing Clough and 11 other group companies into administration on 5 December.

Clough, which specialises in major energy, resources and infrastructure projects, was founded in Western Australia in 1919 and acquired by South African contractor Murray & Roberts in 2013. At the time of its collapse, Clough had 12 companies under its umbrella that together employed 1,250 workers in Australia and a further 1,250 in Papua New Guinea, the United Kingdom and the United States.

The debts

Australian Financial Review infrastructure reporter Jenny Wiggins reported that new filings with the Australian Securities and Investments Commission detail payments owed to Clough’s creditors, including:

  • payables to the Snowy 2.0 joint venture of $88.7 million.
  • more than $12 million owing to AWE Perth – a subsidiary of Mitsui E&P Australia Holdings for work on WA’s Waitsia gas project.
  • some $15.6 million in unpaid leave and super entitlements to Clough employees.
  • $66.6m is owed to hundreds of unsecured trade suppliers and subcontractors.

Clough’s four major secured creditors, HSBC Bank Australia, Liberty Specialty Markets, Assetinsure and AA1, have first call on any funds derived from administration, meaning there is no guarantee that what is owed to trade creditors or the company’s workforce will be paid.

Clough had apparently been struggling financially for an extended period, posting a $375.3 million loss and a $304 million working capital deficit in the last financial year. Like other builders, it was heavily impacted by the COVID-19 pandemic. Supply chain problems and labour shortages resulting from widespread infection contributed to increases in the cost of building materials and caused deadlines to blow out.

Staff exodus

Clough is yet another casualty of the deepening crisis engulfing Australia’s construction industry, which has seen a plethora of building firms go to the wall over the past year, destroying many thousands of jobs.

Uncertainty over whether Webuild would keep the contract to build the WA-based Waitsia gas project site. This led to a staff exodus.

The sale was to save 1000 Clough jobs in Australia, most of them in Perth, but leave Deloitte to sell or break up Clough’s international business, which includes offices in North America, Britain and Papua New Guinea.

Sources told The Australian that 106 white-collar staff, including engineers, had resigned from Clough since the announcement on December 5, and half the blue collar workers had returned to the site in the new year.

The Snowy Hydro Joint Venture

Through their joint entity Future Generation, Clough and Webuild won a $5.1 billion fixed-price contract to build Snowy 2.0 in 2018, but the joint venture has been trying to claim back close to $1 billion of extra costs.

Snowy Hydro will have a new boss from February when the former head of New Zealand’s Contact Energy, Dennis Barnes, becomes chief executive. Mr Barnes replaces Paul Broad, who exited in August after a clash with Federal Energy and Climate Change Minister Chris Bowen.

Takeovers

Webuild may also have the option to extend the scope of the deal to include other Clough projects, but this outcome is far from certain. Deloitte restructuring partner Jason Tracy said only that the administrators had been trying to arrange “interim funding for Clough’s biggest projects by value.”

Webuild’s Mr Salini referred to Clough’s $US1.35 billion ($2 billion) contract to develop a new urea plant for Perdaman Industries on Western Australia’s Burrup Peninsula, in a joint venture with Saipem, as a potential future project for Webuild.

Spanish contractor Acciona is taking over Clough’s $165 million Stephenson Avenue freeway project in Perth.

The Bundaberg Port, awarded to Clough Projects Queensland in July, will be completed by Clough, and is on track.

The Port of Bundaberg is a key site for shipping sugar, timber products and agricultural produce to Australian and overseas suppliers. The Common User Infrastructure (CUI) project to build a multi-purpose bulk goods conveyor received almost $18 million in federal funding. Sugar Terminals Limited (STL) chief executive David Quinn said the company “remains committed” to delivering the facility as soon as possible in 2023.

Meanwhile, Clough said works for the CUI infrastructure were progressing well and it did “not envisage any delays due to the issues that have surrounded other Clough entities over the past week or so.”

The project has been in the pipeline for years, but delays in approvals resulted in the cost blowing out by almost $8 million.

More contracts held by Clough, including the $2.3 billion Project EnergyConnect interconnector cable between South Australia and NSW, and the $768 million Waitsia gas project for Mitsui and Beach Energy in Western Australia, are still up in the air.

Webuild’s global scale and well-lined hip pockets – it has secured some €24 billion ($37.6 billion) in new orders over the past two years, including work on the Inland Rail and the Sydney Metro – is expected to help protect it from some of the cost blowouts encountered by Clough.



You May Also Like

2024 Australian Interior Design Awards reveals a record 222 shortlisted projects

Sustainability, collaboration, and timeless natural materials were this year’s biggest trends.

PropertyGuru Asia Property Awards (Australia) returns for its 7th edition, including several brand new award categories

This year’s awards include several brand new categories, with entries closing 2 August 2024.

Reserve Bank keeps rates on hold at 4.35% for March meeting

The hold was largely predicted, with many experts expecting a rate cut towards the end of this year.

Australia’s inflation rate stays at 3.4%: What it means for borrowers and savers

Annual inflation for January remained steady at 3.4%, signalling stability since November 2021 and a trend towards the RBA’s target band.

Top Articles

PropertyGuru Asia Property Awards (Australia) returns for its 7th edition, including several brand new award ...

This year's awards include several brand new categories, with entries closing 2 August 2024.

Housing crisis survival guide: How to buy your first Australian property

Three property experts give the low down on how to nab a home in this tough housing market.

Strata properties as investments: All you need to know about investing in a Perth unit

As the cost of renting approaches the cost of a mortgage, more people are investing in units to escape the rental trap.